•AOE network
–Edge represents task or activity to be performed on a project
–Vertex represents event which signal the completion of certain activities
•Remarks on AOE
–Determine the minimum amount of time required to complete a project
–An assessment of the activities whose duration should be shortened to reduce the overall completion time
•Evaluate performance
–activity whose duration time should be shortened
–minimum amount of time
•Critical path
–A path that has the longest length
–Minimum time required to complete the project